Final Bill Basement Earth and Footing Work
march 28, 2007
- sink hole: expose and remove contaminated dirt from in and around sink hole underneath basement slab and foundation wall
- bracing: extensively brace floor joists and joist beams to north side of house
- dumping: remove approximately 5 yards of dirt and dispose of at local "Pacific Top soils" plant. Pay all dumping and transport fees
- C.D.F. : place 5 yards of controlled density fill in basement excavation. pay all product, delivery, and pumping fees
- gravel: purchase, deliver, & place 3" layer of crushed rock
- concrete: purchase, deliver, place, & finish top 3" of basement floor with premium concrete product
Labor & Materials with tax: $ 3500.00
No comments:
Post a Comment